VALDOR

The customer's needs

The Valdor hospital – housing care units, geriatrics and (neurological and locomotor) rehabilitation, a residential palliative care unit, specialised consultations and a day hospital – is a historic building which has long been left to deteriorate.

CS_Hôpital
CS_Hôpital
 

The constraints

The best way to reconcile the old and the new.

CS_Hôpital

CS_Hôpital

4m Group's solution

The products

In the new areas, the choice of design was notably reflected in the frescoes on the floor.
Resin was chosen for the public areas as well as the kitchen and cafeterias.
According to the requirements of the different areas, 4m Group used:

Flowfresh HF: 480 m2

Flowfresh MF: 1390 m2

Baseboard Flowfresh: 990 m2

PU Design: 1674 m2

The 4m Group service

4m Group planned 355 work days divided according to need among the three main phases of the project.

Contact us

Defaut